Preparing For Liner Installation | Tampa Plumbers

In this video Ryan Pelky and Dennis Gray are in the process of exposing a ten foot section of cast iron pipe and preparing to reinstate the lateral. Unfortunately, the Coast Guard didn’t approve this phase of the work until 12pm, making it impossible to get additional laborers on the job site. Dennis and Ryan had to dig this out by themselves in order to stay on schedule. After getting down to the pipe we cut out the lateral tie-in using a Spartan 300 cable machine with Magnum inner-core cable and a hole saw. This reinstatement took six hours to complete because the liner had excess resin in it. Click for more information on Spartan cable machines.